• robinm
    link
    fedilink
    arrow-up
    2
    arrow-down
    1
    ·
    edit-2
    1 year ago

    I never had to use this estimate in front of a client, but if I had, I would decompose it first before giving the total estimate. If there is about 10 items to do per button, so 10 buttons would be a hundred complexe tasks. So let say that it take an hour per task, but since we are fast we can do 10 a day. So suddenly 10 working days, or said otherwise 2 weeks don’t seems unrealistics for this apparently simple 10 buttons task.