Summary

France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.

The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.

President Macron hailed the launch as a key step for low-carbon energy and energy security.

Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”

        • Iceblade@lemmy.world
          link
          fedilink
          English
          arrow-up
          1
          ·
          8 hours ago

          Yet the prior means that France is one of the least carbon intensive economies in the world. Each German unit of GDP has twice the CO2 emissions compared to France.

        • Saleh@feddit.org
          link
          fedilink
          English
          arrow-up
          1
          arrow-down
          2
          ·
          1 day ago

          Germany has mostly old coal. Gas is relatively new. I totally agree that Germany needs to do more for its renewable production, like many other European countries need to do. However on a cost per energy level, renewables are beating all other production methods currently known.

    • einkorn@feddit.org
      link
      fedilink
      English
      arrow-up
      6
      arrow-down
      3
      ·
      2 days ago

      Even worse then. Costs per kWH Solar have been sinking faster than some Russian battleships.

        • einkorn@feddit.org
          link
          fedilink
          English
          arrow-up
          2
          arrow-down
          3
          ·
          1 day ago

          What’s your point? Solar getting cheaper and cheaper has nothing to do with Germany. Our booming solar industry got axed by conservatives years ago.